designation: shelter and toilet block
The project we are showing is mainly composed of a covered area and stage
Total surface area of the operation: 140 m² floor space and 0 m² grounds space;
The total construction cost: 134 445 euros tax and fees included.
The price per square meter of the construction: 1 037 euros tax and fees included.
The exact location of the project is in Forêt de Villecartier (Ille-et-Vilaine).
forêt domaniale de Villecartier, Bazouges la Perouse.
The type of location is: rural.
This site can be visited.
The specific materials used: wood and rusted steel.
The main color of the project: wood / rust tones.
The time elapsed from contract to completion 12 months
We are un atelier started in 2006
I work alone
The general number of people having participated, closely or from a distance, in the completion of the project:
1 architect, 1 engineer, 1 companie.
The total of interlocutors, sponsors or people representing the project management made up ", make up total to 3.
This makes trop grand.
The nicest remark made about this project: "From a distance it looks like a bird in flight..."