designation: town hall
The project we are showing is mainly composed of the reconstruction of the town hall on the same site while conserving some of the walls of the old building.
Total surface area of the operation: 1700 m² floor space and 5000 m² grounds space;
Type of layout: new.
The total construction cost: 2 600 000 euros tax and fees included.
The total grounds planning cost: 500 000 euros tax and fees included.
The price per square meter of the construction: 1 530 euros tax and fees included.
The exact location of the project is in Relecq kérhuon (Finistère).
place de la Mairie.
The type of location is: Urbain.
This site can be visited.
The specific materials used: Movable aluminium strips.
The main color of the project: Beige.
The time elapsed from contract to completion 3 years
We are une agence started in 2000
We are a team of 21 people ,
Our practice has 6 qualified architects et 2 students
The general number of people having participated, closely or from a distance, in the completion of the project:
2 architects, 3 engineers, 18 companies, 1 inspector.
The total of interlocutors, sponsors or people representing the project management made up ", make up total to 10.
This makes très grand.
The nicest remark made about this project: “An ecological building restructuring the town center.”